Project Overview
Keeping a Waterlogged Site Moving
Wet ground threatened progress on a tightly programmed warehousing development in St Ives. Approximately 2,000m2 required drying before works could continue, with no improvement in the weather expected for several days. Furlong GS worked with the site team to treat the existing material rather than export it and bring in replacement capping. Earthworks were undertaken by the main contractor.
Lime Treatment and Cement Stabilisation
Hydrated lime was used to condition the made ground to a workable moisture content, with the source case study identifying an optimum moisture range of 18-22% for this material. This is a project-specific range, not a general treatment specification. CEM II cement was then used to provide the stabilised cement-bound pavement foundation layer, replacing imported capping with a 300mm treated layer.
In-House Testing and Verification
Testing was undertaken by a Furlong GS in-house technician. The project documentation includes moisture condition value testing and bearing verification, supporting the design and delivery of the site drying and capping replacement works.
Project and Client Benefits
The design and delivery package enabled the client to reuse site-won material, saving time and money. The case study reports 50% cost saving, 45% programme reduction, 80% fewer vehicle movements, 80% less imported aggregate, 100% less material sent to landfill and 50% less stone layer depth. These are reported benefits for this project, rather than guarantees for other sites.