St Ives Soil Drying and Capping Replacement

Soil and Site Drying

St Ives Soil Drying and Capping Replacement

Furlong GS provided a design and delivery package for a warehousing developer in St Ives, treating wet made ground for reuse and constructing a stabilised capping replacement layer.

St Ives 5 days

Project Overview

Keeping a Waterlogged Site Moving

Wet ground threatened progress on a tightly programmed warehousing development in St Ives. Approximately 2,000m2 required drying before works could continue, with no improvement in the weather expected for several days. Furlong GS worked with the site team to treat the existing material rather than export it and bring in replacement capping. Earthworks were undertaken by the main contractor.

Lime Treatment and Cement Stabilisation

Hydrated lime was used to condition the made ground to a workable moisture content, with the source case study identifying an optimum moisture range of 18-22% for this material. This is a project-specific range, not a general treatment specification. CEM II cement was then used to provide the stabilised cement-bound pavement foundation layer, replacing imported capping with a 300mm treated layer.

In-House Testing and Verification

Testing was undertaken by a Furlong GS in-house technician. The project documentation includes moisture condition value testing and bearing verification, supporting the design and delivery of the site drying and capping replacement works.

Project and Client Benefits

The design and delivery package enabled the client to reuse site-won material, saving time and money. The case study reports 50% cost saving, 45% programme reduction, 80% fewer vehicle movements, 80% less imported aggregate, 100% less material sent to landfill and 50% less stone layer depth. These are reported benefits for this project, rather than guarantees for other sites.

The Challenge

  • Approximately 2,000m2 of the site was too wet and waterlogged for construction works to continue without treatment.
  • The works programme was tight and the weather was not expected to improve for several days.
  • The client needed a solution that avoided exporting wet material and importing a replacement capping layer.

The Solution

  • Worked closely with the site team to develop a design and delivery package for site drying and capping replacement.
  • Used hydrated lime to condition the wet made ground towards the project-specific optimum moisture range of 18-22%.
  • Used CEM II cement to provide a 300mm stabilised cement-bound pavement foundation layer.
  • Undertook testing through a Furlong GS in-house technician, including moisture condition value and bearing checks.

The Outcome

  • Enabled site-won material to be reused to create the capping replacement layer.
  • Delivered the approximately 2,000m2 treatment area within the reported 5-day programme.
  • The case study reports 50% cost saving, 45% programme reduction and 80% fewer vehicle movements.
  • The reported material benefits are 80% less imported aggregate, 100% less material sent to landfill and 50% less stone layer depth.